All projects: Construction updates, October 2026

A group of people sitting around a table in a classroom-like setting, with a projection screen visible in the background.

Great work continues on our construction projects, with one that has just been completed! Here is a summary of updates. Click on each project for details. We thank our voters, who approved the November 2024 construction bond, making these projects possible. Stay up to date on our progress at sumnerbonneylakebuilds.org.


Bonney Lake High School Expansion & Intersection

New welcome center, 18 classrooms, administration and student services area, turf and lighted baseball and fastpitch fields; new two-lane roundabout intersection 

Completed: 

  • New piping in 500 wing 
  • New schoolwide LED lighting 
  • New temporary school office/administrative area 
  • Temporary wall in commons to separate occupied areas from construction 

Up next: 

  • Demolition of the school’s former upper campus entrance, office and administration area: Begins Oct. 12
  • Improved intersection between BLHS and Mountain View MS: Construction to begin Spring 2027 
  • New turf, lighted fields: Construction to begin Summer 2027 

Estimated completion: Intersection - Fall 2027; Expansion - Fall 2028

A large school cafeteria features numerous tables and chairs in the foreground, with a high ceiling and banners on the walls in the background.

Sumner High School Phase 2 & 3

Phase 2

New classrooms, greenhouse, childcare area, parking

Completed: 

  • Pilings installed
  • Utility tie-ins installed
  • Foundation work

Up next: 

  • Grade beams and structural slabs
  • Structural steel 
Large blue and white cranes operate on a gravel construction site with buildings and forested hills in the background.

Phase 3 

New pool, gym, performing arts center, music/art rooms, administration area, turf fields, parking

Completed: 

  • General Contractor/Construction Manager selected
  • Design contract awarded

Up next: 

  • Schematic design

Estimated completion: Phase 2 - Fall 2028; Phase 3 - Fall 2032


New Middle School in Tehaleh 

New three-story, 900-student middle school with modern learning technology, safety/security systems, multiuse lighted turf fields 

Completed: 

  • Design development
  • Architectural Review Committee approval
  • Purchase and sale agreement executed 

Up next: 

  • Construction documents
  • Permitting
  • Property closing 

Estimated opening: Fall 2029

An empty asphalt road leads toward a dirt lot and a distant line of evergreen trees under a cloudy sky.

Daffodil Valley Elementary / Bill Heath Field Improvements 

New turf and lighted fastpitch and baseball fields, storage building with restrooms, parking, tennis/pickleball courts, basketball and playground. Daffodil Valley: new outdoor learning area, mini-pitch area and a soccer field 

Completed: 

  • Purchased Bill Heath property
  • Updated designs 

Up next: 

  • Closing on Bill Heath property 
  • Design and permitting 

Estimated completion: Outdoor learning area - Fall 2027; Fields - February 2028

Three green baseball diamonds are arranged in the foreground against a white architectural site plan background.

Tehaleh Heights Elementary Expansion 

New 8 classroom addition; expanded parking and improved queueing

Completed: 

  • Design development
  • Integrated design with road expansion 

Up next: 

  • Construction documents
  • Permitting
  • Architectural Review Committee approval 

Estimated completion: Fall 2028

A rendering of modern, multi-story building with a mix of wood and brick siding stands in a grassy area, surrounded by trees and a cloudy sky.

Crestwood and Liberty Ridge Elementary Improvements 

New interior walls, paint, casework, HVAC, flooring, lighting and lighting controls, reconfigured administration and front office, reconfigured special education spaces, revised site queueing

Completed: 

  • Revised scope
  • Estimates

Up next: 

  • Design and permitting
  • Contractor selection
  • State funding applications 

Estimated completion: Summer 2029

People gather in the foreground of a modern school lobby, with a reception desk and %22Crestwood Elementary%22 signage in the background.
A woman sits in a green chair in the foreground, while a mother and child stand at a school reception desk in the background.

Donald Eismann Elementary Improvements

Project completed:

  • New turf, lighted multiuse field
  • Expanded parking
  • Improved queuing 

We look forward to a ribbon cutting celebration soon! 

Five young boys stand in a row on a green turf field, with other children playing and a line of trees in the background.

Energy Efficiency Upgrades

Multi-phase, districtwide LED lighting replacement and upgrades, starting with four schools.  

Completed: 

  • Bonney Lake High School
  • Lakeridge Middle School
  • Mountain View Middle School
  • Sumner Middle School

Watch this video to learn more about the project. 


We’re pleased that a couple of other non-bond projects, funded from Capital Funds, are complete: 

  • Lakeridge Middle School: Expanded parking, improved queueing; fencing around wetland area
Newly constructed Lakeridge entrance
  • Mountain View Middle School: New gym floor, paint, bleachers; remodeled front office/administrative/staff areas 
Completed Mountain View Gym

 

A group of people sitting around a table in a classroom-like setting, with a projection screen visible in the background.
A group of people sitting around a table in a classroom-like setting, with a projection screen visible in the background.